Temple News & Updates | Week of 5 November 2017

Thanks to members of the church worldwide and our friends at LDSChurchTemples.com for providing these updates. If you have updates (including pictures or video) about a temple near you, feel free to send it to calledtoshare (at) ldsdaily.com.

Five Weeks Into Memphis Temple Renovation

Crews have made significant progress on dismantling the interior and exterior of the Memphis Tennessee Temple. Area missionaries have been serving at the site and were given the job of taking apart delicate items like the celestial room chandelier.

Courtesy of Ted Archdeacon

 

Cladding Coming Down in OKC

Progress continues on the Oklahoma City Oklahoma Temple renovation as crews remove pieces of marble cladding from the exterior walls. The temple is expected to reopen in 2019.

Courtesy of Lisa Poling

 

Exterior Walls Complete in South America

Crews are making steady progress on the Arequipa Peru Temple. The walls of the structure were completed this last week, and a large construction crane has been removed from the site.

Courtesy of David Mahas

 

Palm Trees Planted in Colombia

Stately palm trees have been arranged in two rows on the grounds of the Barranquilla Colombia Temple. Cladding is continuing to the temple’s tower and an ornamental cornice is being installed along the roof line.

 

Roof Decking Being Placed In Africa

Crews working on the Durban South Africa Temple have started placing decking atop the roof trusses. The design of the roof will allow the African rains to roll off the roof and will add a distinct aesthetic to the building.

Courtesy of Somerset West Ward

 

Scaffolding Removed in Rome

The towers of the Rome Italy Temple are clearly visible for the first time since steel framing went up in 2013. Interior work is underway. A completion date of the temple has yet to be announced.

Courtesy of Amy Hoagland

 

Progress Continues in Brazil

The site of the Fortaleza Brazil Temple is progressing quickly and smoothly. A vapor barrier and stone cladding are being attached to the temple walls. The adjacent meetinghouse is nearing completion as well. The temple is estimated to be completed by mid-2019, though no official date has been announced.

Courtesy of Ozair Ribeiro Filho

 

More Walls Completed in Portugal

Crews have poured more exterior walls on the Lisbon Portugal Temple. The temple is estimated to be complete in late 2019.

Courtesy of Construction of Lisbon Temple Facebook page

 

Open House Dates & Links to Tickets

Cedar City Utah Temple
Friday 27 October – Saturday 18 November
Tickets Available Here Beginning Monday 2 October 2017

Comments

comments

About Natalie Bruce

Natalie Bruce
Natalie is a graduate of Brigham Young Unversity, where she studied Communications and Editing. She is passionate about the Northern California coast, reading biographies, and the Oxford comma.
Free LDS Daily Emails!
Get inspiring LDS messages, news, and events sent to your email inbox daily, weekly, or monthly!
No, thank you.